Metal decking over is approximately 95% complete over both levels. Connections and fastening of the decking is not complete yet. Mechanical and electrical have resumed rough-in and stub ups at grade. Workers will be progressing through to the second floor … Continue reading Civic Centre Resource Library – May 1